Water Storage Tank Replacement — Barre, Massachusetts

LEI provided land surveying, geotechnical investigation, improvement recommendations, engineering and environmental reports, design plans and specifications, construction cost estimates, assistance with the preparation of USDA grant and loan documents, permitting (local conservation commission for wetlands and MA DEP for drinking water), construction documents, project bidding, construction administration, and on-site inspection for the Sanderson Road Water Storage Tank, access roadway and site improvements. The 500,000-gallon, pre-stressed concrete tank is 58 feet in diameter and 32 feet tall.

<